Exam CIS-PPM topic 1 question 73 discussion

Actual exam question from ServiceNow's CIS-PPM
Question #: 73
Topic #: 1
[All CIS-PPM Questions]

What are the possible breakdown types of a cost plan breakdown? (Choose four.)

  • A. Demand
  • B. Requirement
  • C. Project
  • D. Task
  • E. Portfolio
  • F. Program
Show Suggested Answer Hide Answer
Suggested Answer: BDEF 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
formacion_teamnow
3 weeks, 1 day ago
Selected Answer: ACEF
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html "A cost plan breakdown captures the estimated cost and actual cost for every fiscal period. Cost plan, project, demand, program, and portfolio are the breakdowns types that are available."
upvoted 1 times
...
formacion_teamnow
4 weeks, 1 day ago
Selected Answer: BDEF
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html
upvoted 1 times
formacion_teamnow
3 weeks, 1 day ago
This answer is mine and is wrong, if an admin can delete it, please do it
upvoted 1 times
...
...
AnnaMr
1 month ago
Selected Answer: BDEF
The cost plan breakdown has a field breakdown type with the values- requirement, task, program and portfolio
upvoted 1 times
...
formacion_teamnow
1 month ago
Selected Answer: BDEF
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html Moreover, if you go to your PDI, look for a cost_plan_breakdown and you look at the choice list of the field "breakdown type", the string available are requirement, task, portfolio and program
upvoted 1 times
...
formacion_teamnow
1 month ago
Selected Answer: BCEF
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html Moreover, if you go to your PDI, look for a cost_plan_breakdown and you look at the choice list of the field "breakdown type", the string available are requirement, task, portfolio and program
upvoted 1 times
...
a5aa8f2
1 month, 3 weeks ago
Selected Answer: ACEF
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html Clearly states "project, demand, program, and portfolio are the breakdowns types that are available."
upvoted 1 times
...
Bodybuildingfly
6 months, 2 weeks ago
Selected Answer: ACEF
https://docs.servicenow.com/bundle/utah-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html A cost plan breakdown captures the estimated cost and actual cost for every fiscal period. Cost plan, project, demand, program, and portfolio are the breakdowns types that are available.
upvoted 3 times
...
220052
8 months, 1 week ago
Selected Answer: BDEF
checked Project Portfolio Management (PPM) Implementation Simulator Cost Plan Breakdowns https://docs.servicenow.com/ja-JP/bundle/utah-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html
upvoted 2 times
...
220052
8 months, 2 weeks ago
Please tell me this answer, ACEForBDEF
upvoted 1 times
...
Luiza25
11 months ago
A cost plan breakdown captures the estimated cost and actual cost for every fiscal period. Cost plan, project, demand, program, and portfolio are the breakdowns types that are available.
upvoted 2 times
...
patff123
1 year ago
BDEF is correct. There is a column called "breakdown type" in cost_plan_breakdown table which choices are: Requirement, Task, Program, Portfolio.
upvoted 3 times
sagace77
3 months ago
I agree! It is enough to display the choices available for this field!
upvoted 1 times
...
...
VSbrissa
1 year ago
Selected Answer: ACEF
correct
upvoted 1 times
...
Zolly
1 year ago
Selected Answer: ACEF
https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html Demand, Project, Portfolio, Program
upvoted 3 times
YARON_R
9 months, 1 week ago
Sorry, but the right answer is BDEF https://docs.servicenow.com/en-US/bundle/utah-it-business-management/page/product/project-management/concept/cost-plan-breakdown.html
upvoted 2 times
...
...
1307199725
1 year, 1 month ago
Selected Answer: BDEF
BDEF is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...