Answer:
A. Expiration
C. Reassignment
Explanation: there are 4 notifications OOB related to Audit Task[sn_audit_task]
- Notify audit task confidential users
- Notify current assingee task expired | A.
- Notify assignee before due date
- Change assigned to of audit task | C.
Source: PDI, sysevent_email_action list view, with filter: sys_scope.nameLIKEGrc^collection=sn_audit_task
C is correct doubt on another one
https://docs.servicenow.com/en-US/bundle/utah-governance-risk-compliance/page/product/grc-audit/concept/c_AuditTasks.html
When audit tasks are created or reassigned, a notification is sent to the assigned user. A notification is also sent when the task reaches 75% of its planned duration.
This section is not available anymore. Please use the main Exam Page.CIS-RC Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
sephereth
7 months, 3 weeks agoss2780
1 year, 6 months agoss2780
1 year, 6 months agoPRAFUL99
1 year, 9 months agoLivut
1 year, 2 months ago