What is the formula for Forecasted Utilization?

  • A. Assigned Hours/Capacity
  • B. Confirmed Hours/Capacity
  • C. (Allocated Hours + Confirmed Hours)/Capacity
  • D. Allocated Hours/Capacity
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Edmundas
6 days ago
Selected Answer: C
The correct answer is C Forecasted Utilization Percentage of forecasted resource time utilization. It is calculated as sum of allocated and confirmed hours, divided by the total capacity. https://www.servicenow.com/docs/bundle/yokohama-it-business-management/page/product/resource-management/concept/c_UsingResourceManagementReports.html#:~:text=Forecasted%20Utilization,the%20total%20capacity.
upvoted 1 times
...
SNSN23
6 days, 2 hours ago
Selected Answer: C
Forecasted Utilization Percentage of forecasted resource time utilization. It is calculated as sum of allocated and confirmed hours, divided by the total capacity. ref: https://www.servicenow.com/docs/bundle/xanadu-it-business-management/page/product/resource-management/concept/c_UsingResourceManagementReports.html
upvoted 1 times
...
099b115
3 weeks, 6 days ago
Selected Answer: C
100% is C
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...