The correct answer is C
Forecasted Utilization
Percentage of forecasted resource time utilization. It is calculated as sum of allocated and confirmed hours, divided by the total capacity.
https://www.servicenow.com/docs/bundle/yokohama-it-business-management/page/product/resource-management/concept/c_UsingResourceManagementReports.html#:~:text=Forecasted%20Utilization,the%20total%20capacity.
Forecasted Utilization
Percentage of forecasted resource time utilization. It is calculated as sum of allocated and confirmed hours, divided by the total capacity.
ref: https://www.servicenow.com/docs/bundle/xanadu-it-business-management/page/product/resource-management/concept/c_UsingResourceManagementReports.html
This section is not available anymore. Please use the main Exam Page.CIS-SPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Edmundas
6 days agoSNSN23
6 days, 2 hours ago099b115
3 weeks, 6 days ago