Planned cost is rolled up from Requested Allocations for plans in the Planning or Requested state and from Resource allocations for plans in the Confirmed or Allocated state. While requesting resources from a group, if a resource role is specified, the planned cost is calculated from the hourly rate of the specified role.
https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/resource-management/reference/rsrc-plan-form-tabs.html