What must a resource plan contain if a resource plan is associated with a time card?

  • A. Front load allocation spread.
  • B. Hard allocation bookings.
  • C. Even allocation spread.
  • D. Soft allocation bookings.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Edmundas
2 months ago
Selected Answer: B
The correct answer is B A resource plan can be associated with a time card only if the resource plan contains hard allocations for the user. https://www.servicenow.com/docs/bundle/yokohama-it-business-management/page/product/resource-management/task/t_AssocATimeCardWithAResourcePlan.html
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...