Question #: 44
Topic #: 1
[All OGEA-103 Questions]

Please read this scenario prior to answering the question.
Your role is that of a consultant to the Lead Enterprise Architect in a multinational automotive manufacturer. The company has a corporate strategy that focuses on electrification of its portfolio and it has invested heavily in a new shared car platform to use across all its brands. The company has four manufacturing facilities, one in North America two in Europe and one in Asia.
A challenge that the company is facing is to scale up the number of vehicles coming off the production line to meet customer demand, while maintaining quality. There are significant supply chain shortages for electronic components, which are impacting production in response to this the company has taken on new suppliers and has also taken design and production of the battery pack in-house.
The company has a mature Enterprise Architecture practice. The TOGAF standard is used for developing the process and systems used to design, manufacture, and test the battery pack. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
As part of putting the new battery pack into production adjustments to the assembly processes need to be made. A pilot project has been completed at a single location. The Chief Engineer, sponsor of the activity and the Architecture Board have approved the plan for implementation and migration at each plant.
Draft Architecture Contracts have been developed that detail the work needed to implement and deploy the new processes for each location. The company mixes internal teams with a few third-party contractors at the locations. The Chief Engineer has expressed concern that the deployment will not be consistent and of acceptable quality.
Refer to the scenario.
The Lead Enterprise Architect has asked you to review the draft Architecture Contracts and recommend the best approach to address the Chief Engineer's concern.
Based on the TOGAF Standard, which of the following is the best answer?

  • A. For changes requested by an internal team, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to third-party contractors, you recommend that it is a fully enforceable legal contract. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • B. You recommend that the Architecture Contracts be used to manage the architecture governance processes across the locations. You recommend deployment of monitoring tools to assess the performance of each completed battery pack at each location and develop change requirements if necessary. If a deviation from the contract is detected the Architecture Board should allow the Architecture Contract to be modified meet the local needs. In such cases they should issue a new Request for Architecture Work to implement a modification to the Architecture Definition.
  • C. For changes undertaken by internal teams, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. If a contract is issued to a contractor, you recommend that it is a fully enforceable legal contract. If a deviation from the Architecture Contract is found, you recommend that the Architecture Board grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • D. You review the contracts ensuring that they address project objectives, effectiveness metrics, acceptance criteria, and risk management. Third-party contracts must be legally enforceable. You recommend a schedule of compliance reviews at key points in the implementation process. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the process to be customized for local needs.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jeenia
1 month ago
Selected Answer: D
D is the right answer. It directly addresses the question asked - about reviewing the architecture contract. Other options do not talk about reviewing the contract, rather suggest/recommend other alternatives. Hence, those can be easily discarded.
upvoted 1 times
...
Jeenia
1 month ago
D is the right answer. It directly addresses the question asked - about reviewing the architecture contract. Other options do not talk about reviewing the contract, rather suggest/recommend other alternatives. Hence, those can be easily discarded.
upvoted 1 times
...
MMStrong
3 months, 1 week ago
D - Agreed with HKWong. Dispensation grant is the key here.
upvoted 1 times
...
hkwong
4 months ago
Selected Answer: D
D. Review the objectives, acceptance criteria to address quality; Dispensation grant is needed to address local need
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...