Complete the following sentence. In the ADM, documents which are under development and have not undergone any formal review and approval process are _______.
The TOGAF standard specifies that documents which are under development and have not undergone formal review or approval are typically labeled with an initial version number such as Version 0.1. This versioning indicates that the document is still in draft form and subject to revisions.
Once the document has been formally reviewed and approved, it progresses to Version 1.0 or higher.
Therefore, D is the correct choice.
https://pubs.opengroup.org/togaf-standard/adm/chap01.html
1.2.2 Basic Structure
In the ADM, documents which are under development and have not undergone any formal review and approval process are designated "draft".
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
lucaluca1982
3 weeks, 3 days agoKareemq
3 weeks, 3 days agosujithkp
4 months, 4 weeks agoklezlil
5 months, 3 weeks ago