Actual exam question from Vmedu's Scrum Master Certified
Question #: 2
Topic #: 1
[All Scrum Master Certified Questions]

A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?

  • A. Detailed upfront planning will be done to ensure that risks are identified early on.
  • B. The team working on this project will meet every day for 15 minutes to list impediments to completing their tasks.
  • C. The Product Owner will prioritize the tasks that deliver maximum business value.
  • D. The customer does not have to be able to define very concrete requirements early on.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
asbok
Highly Voted 1 year, 2 months ago
A. Page 133 of SBOK Guide 7.8 Scrum vs. Traditional Project Management
upvoted 6 times
...
patricpotter1992
Most Recent 6 months ago
Answer: A
upvoted 2 times
...
ekmode
1 year, 1 month ago
Answer :A
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.