Question #: 34
Topic #: 1
[All 2V0-11.25 Questions]

An administrator needs to scale an NSX Edge cluster by adding additional Edge nodes.
Which three steps must be taken before scaling an Edge cluster from SDDC Manager? (Choose three.)

  • A. Assign a unique management IP for each Edge node.
  • B. Assign two Tunnel Endpoint (TEP) addresses for each Edge node.
  • C. Add an additional NSX VDS uplink for each Edge node being added.
  • D. Verify DNS records have been added for each new Edge node.
  • E. Place the Edge cluster in maintenance mode prior to expanding.
Show Suggested Answer Hide Answer
Suggested Answer: ABD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
9e7c4f1
1 month, 3 weeks ago
Selected Answer: ABD
ABD Each node must have a unique management IP. Each node must have a unique Edge TEP 1 IP. Each node must have a unique Edge TEP 2 IP. The Edge TEP 2 IP must be different than the Edge TEP 1 IP. Verify that DNS entries for the NSX Edge nodes are populated in the customer-managed DNS server. https://techdocs.broadcom.com/us/en/vmware-cis/vcf/vcf-5-2-and-earlier/4-5/administering/deploying-nsx-edge-clusters-admin/add-edge-nodes-to-an-nsx-edge-cluster-admin.html
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...