One of the datastores containing a linked clone desktop pool is running out of disk space and an administrator adds a second datastore. Which operation should the administrator perform to resolve the issue?
D- Rebalance - A rebalance operation evenly redistributes linked-clone virtual machines among available datastores
https://docs.vmware.com/en/VMware-Horizon-7/7.0/com.vmware.horizon-view.administration.doc/GUID-1258E651-0A9F-4A71-AD59-F3CD57072E41.html
This question is also on the exam:
One of the datastores containing a manual desktop pool is running out of disk space and an administrator adds a second datastore.
Which operation should the administrator perform to resolve the issue?
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
jerryu_knows
Highly Voted 5 years, 6 months agobambangka
Most Recent 3 years, 6 months agoMBA007
3 years, 7 months agojuancarlosmarquezc
4 years, 3 months agoYurets
4 years, 10 months agoStacey
4 years, 11 months agojasontch
4 years, 7 months agov_admin
5 years agoAJ123
5 years agovmwarelive
5 years, 6 months agoCarbonfiber01
5 years, 6 months ago