Your company-managed kanban project has a total of six statuses in the workflows. Which statement about the kanban board is true?
Correct Answer:
C
🗳️
5 development teams need to work across 3 projects and plan their iterations in a single board.
Which board supports this?
Correct Answer:
D
🗳️
You are the project administrator of two Scrum projects, MOBI and TIS.
Team members find it difficult to switch between both projects to work on separate sprints.
They need the ability to work on issues from both projects in a single sprint.
Identify two ways that you can satisfy this requirement. (Choose two.)
Correct Answer:
CE
🗳️
Marcella can see TIS issues but not the TIS project board.
Identify the reason why.
Correct Answer:
A
🗳️