Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
sale

Want to Unlock All Questions for this Exam?

Full Exam Access, Discussions, No Robots Checks

CompTIA PK0-004 Exam Actual Questions

The questions for PK0-004 were last updated on March 30, 2024.
  • Viewing page 1 out of 101 pages.
  • Viewing questions 1-10 out of 1004 questions

Topic 1 - Single Topic

Question #1 Topic 1

A project manager is attempting to establish the proper sequencing and duration of project activities.
Which of the following would be the MOST beneficial?

  • A. Network diagram
  • B. Ishikawa diagram
  • C. WBS
  • D. Gantt chart
Reveal Solution Hide Solution   Discussion   13

Correct Answer: A 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160

Question #2 Topic 1

Which of the following are characteristics of a project? (Choose two.)

  • A. Ongoing
  • B. Temporary
  • C. Start and finish
  • D. Achieving a goal
  • E. Consisting of milestones
  • F. Restricting the budget
Reveal Solution Hide Solution   Discussion   6

Correct Answer: BC 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27

Question #3 Topic 1

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.
Which of the following documents will the company MOST likely release FIRST?

  • A. RFO
  • B. RFI
  • C. RFP
  • D. RFQ
Reveal Solution Hide Solution   Discussion   1

Correct Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300

Question #4 Topic 1

The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)

  • A. The issue log to show why the vendor should be replaced.
  • B. The team action items to show why the vendor should be replaced.
  • C. The scope statement to show why the vendor should be replaced.
  • D. A procurement plan to show why the vendor should be replaced.
  • E. A change management plan to have the vendor replaced.
Reveal Solution Hide Solution   Discussion   3

Correct Answer: AE 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 291, p. 327

Question #5 Topic 1

A project manager is creating the WBS.
In which of the following phases is the project?

  • A. Initiation
  • B. Planning
  • C. Execution
  • D. Closing
Reveal Solution Hide Solution   Discussion   3

Correct Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 139

Question #6 Topic 1

Which of the following is a characteristics of a matrix organization?

  • A. Authority lies solely with the project manager.
  • B. Authority is directed by the project architect.
  • C. Authority is shared between the project manager and project coordinator.
  • D. Authority is shared between functional and project managers.
Reveal Solution Hide Solution   Discussion   2

Correct Answer: D 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 56

Question #7 Topic 1

A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

  • A. Project team members
  • B. Project sponsor
  • C. Project manager
  • D. Project scheduler
Reveal Solution Hide Solution   Discussion   13

Correct Answer: B 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82

Question #8 Topic 1

A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?

  • A. Project schedule
  • B. Balanced scorecard
  • C. Issue log
  • D. Status report
Reveal Solution Hide Solution   Discussion   1

Correct Answer: D 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328

Question #9 Topic 1

A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

  • A. Status report
  • B. Organizational chart
  • C. RACI matrix
  • D. Meeting minutes
  • E. Communication plan
Reveal Solution Hide Solution   Discussion   14

Correct Answer: AD 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 261

Question #10 Topic 1

There are four parallel paths on a network diagram. The summary duration of each path is below:

A, C, G: 10 weeks -

A, B, F: 8 weeks -

D, E, H: 12 weeks -

D, B, F: 7 weeks -
Which of the following tasks are on the critical path?

  • A. A, C, G
  • B. A, B, F
  • C. D, E, H
  • D. D, B, F
Reveal Solution Hide Solution   Discussion   2

Correct Answer: C 🗳️
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...