Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
sale

Want to Unlock All Questions for this Exam?

Full Exam Access, Discussions, No Robots Checks

PMI CAPM Exam Actual Questions

The questions for CAPM were last updated on April 13, 2024.
  • Viewing page 1 out of 45 pages.
  • Viewing questions 1-10 out of 452 questions

Topic 1 - Single Topic

Question #1 Topic 1

Once the make-or-buy analysis is completed, which document defines the project delivery method?

  • A. Procurement statement of work (SOW)
  • B. Procurement strategy
  • C. Terms of reference
  • D. Change request
Reveal Solution Hide Solution   Discussion   18

Correct Answer: B 🗳️

Question #2 Topic 1

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholder, is correct?

  • A. The project manager should identify and deal with stakeholders only during the execution phase.
  • B. Stakeholder satisfaction should be identified immediately and managed as a project objective.
  • C. The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • D. Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Reveal Solution Hide Solution   Discussion   4

Correct Answer: B 🗳️

Question #3 Topic 1

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

  • A. Hybrid methodologies
  • B. Risk register updates
  • C. Outsourced project resources
  • D. Reliance on lessons learned documents
Reveal Solution Hide Solution   Discussion   10

Correct Answer: A 🗳️

Question #4 Topic 1

What should a project manager use to determine how much money is needed to complete a project?

  • A. Earned value management (EVM)
  • B. Estimate at completion (EAC)
  • C. Earned value analysis (EVA)
  • D. Budget at completion (BAC)
Reveal Solution Hide Solution   Discussion   13

Correct Answer: C 🗳️

Question #5 Topic 1

The project manager is creating the communications management plan. Which group of inputs is required to begin?

  • A. Work performance reports, change requests, and risk register
  • B. Work performance data, project documents, and stakeholder engagement plan
  • C. Project charter, project management plan, and project documents
  • D. Work performance data, stakeholder register, and team management plan
Reveal Solution Hide Solution   Discussion   8

Correct Answer: C 🗳️

Question #6 Topic 1

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

  • A. create the project management plan.
  • B. identify the project objectives.
  • C. review and update stakeholder engagement.
  • D. create the schedule baseline.
Reveal Solution Hide Solution   Discussion   8

Correct Answer: C 🗳️

Question #7 Topic 1

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified.
How many communication channels are available?

  • A. 8
  • B. 18
  • C. 36
  • D. 40
Reveal Solution Hide Solution   Discussion   7

Correct Answer: C 🗳️

Question #8 Topic 1

A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?

  • A. Review stakeholder register and meeting
  • B. Data analysis and communication skills
  • C. Data gathering and data analysis
  • D. Communication skills and cultural awareness
Reveal Solution Hide Solution   Discussion   14

Correct Answer: B 🗳️

Question #9 Topic 1

Select three processes that are associated with Project Schedule Management? (Choose three.)

  • A. Define Activities
  • B. Plan Resource Management
  • C. Estimate Activity Durations
  • D. Develop Schedule
  • E. Acquire Resources
Reveal Solution Hide Solution   Discussion   4

Correct Answer: ACD 🗳️

Question #10 Topic 1

What are the project management processes associated with project quality management?

  • A. Plan Quality Management, Manage Quality, and Control Quality
  • B. Plan Quality Management, Manage Quality, and Cost of Quality
  • C. Manage Quality, Customer Satisfaction, and Control Quality
  • D. Customer Satisfaction, Control Quality, and Continuous Improvement
Reveal Solution Hide Solution   Discussion   5

Correct Answer: A 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...