Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

PMI CAPM Exam Actual Questions

The questions for CAPM were last updated on Sept. 9, 2023.
  • Viewing page 1 out of 57 pages.
  • Viewing questions 1-5 out of 292 questions

Topic 1 - Single Topic

Question #1 Topic 1

Once the make-or-buy analysis is completed, which document defines the project delivery method?

  • A. Procurement statement of work (SOW)
  • B. Procurement strategy
  • C. Terms of reference
  • D. Change request
Reveal Solution Hide Solution   Discussion   16

Correct Answer: B 🗳️

Question #2 Topic 1

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholder, is correct?

  • A. The project manager should identify and deal with stakeholders only during the execution phase.
  • B. Stakeholder satisfaction should be identified immediately and managed as a project objective.
  • C. The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • D. Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Reveal Solution Hide Solution   Discussion   3

Correct Answer: B 🗳️

Question #3 Topic 1

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

  • A. Hybrid methodologies
  • B. Risk register updates
  • C. Outsourced project resources
  • D. Reliance on lessons learned documents
Reveal Solution Hide Solution   Discussion   8

Correct Answer: A 🗳️

Question #4 Topic 1

What should a project manager use to determine how much money is needed to complete a project?

  • A. Earned value management (EVM)
  • B. Estimate at completion (EAC)
  • C. Earned value analysis (EVA)
  • D. Budget at completion (BAC)
Reveal Solution Hide Solution   Discussion   9

Correct Answer: C 🗳️

Question #5 Topic 1

The project manager is creating the communications management plan. Which group of inputs is required to begin?

  • A. Work performance reports, change requests, and risk register
  • B. Work performance data, project documents, and stakeholder engagement plan
  • C. Project charter, project management plan, and project documents
  • D. Work performance data, stakeholder register, and team management plan
Reveal Solution Hide Solution   Discussion   7

Correct Answer: C 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...