Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
sale

Want to Unlock All Questions for this Exam?

Full Exam Access, Discussions, No Robots Checks

PRINCE2 PRINCE2-Practitioner Exam Actual Questions

The questions for PRINCE2-Practitioner were last updated on April 15, 2024.
  • Viewing page 1 out of 38 pages.
  • Viewing questions 1-10 out of 377 questions

Topic 1 - Question Set 1

Question #1 Topic 1

Which of the following statements describes an outcome?

  • A. Any of the projects specialist products
  • B. A result of the change derived from using the project's products
  • C. A measurable improvement resulting from a change
  • D. Something perceived as advantages by a stakeholder
Reveal Solution Hide Solution   Discussion   2

Correct Answer: B 🗳️

Question #2 Topic 1

Which of the following should NOT be included in the business case?

  • A. Reasons
  • B. Major Risks
  • C. Business options
  • D. Business approach
Reveal Solution Hide Solution   Discussion   2

Correct Answer: D 🗳️

Question #3 Topic 1

When considering the business options in the business case, which of these is NOT an option?

  • A. Do nothing
  • B. Do the maximum
  • C. Do the minimum
  • D. Do something
Reveal Solution Hide Solution   Discussion   1

Correct Answer: B 🗳️

Question #4 Topic 1

Which of the following statements is TRUE with regard to expected benefits?

  • A. They cannot be assigned
  • B. They don't need to follow corporate objectives
  • C. They should be measurable
  • D. Tolerances cannot be set against expected benefits
Reveal Solution Hide Solution   Discussion   1

Correct Answer: C 🗳️

Question #5 Topic 1

Who is responsible for ensuring that the value-for-money solution is constantly reassessed?

  • A. Business Assurance
  • B. Senior User
  • C. Corporate or Programme Management
  • D. Reject Support
Reveal Solution Hide Solution   Discussion   5

Correct Answer: A 🗳️

Question #6 Topic 1

Which of the following activities is the Executive responsible for?

  • A. Ensure the desired outcome of the project is specified
  • B. Responsible for the benefits review plan
  • C. Assess and update the Business Case at the end of each stage
  • D. Responsible for the Benefits Review Plan post project
Reveal Solution Hide Solution   Discussion   4

Correct Answer: B 🗳️

Question #7 Topic 1

DRAG DROP -

BUSINESS CASE -
Here are three statements from the business case for the Health and Safety Project.
Under which heading in the business case (A-F) should they be recorded?
Choose only one heading for each statement. Each heading can be used once, more than once, or not at all.
Select and Place:

Reveal Solution Hide Solution   Discussion   5

Correct Answer:

Question #8 Topic 1

The executive has asked the project manager to plan for the 'e-learning course' to be used as soon as it is accredited. The aim is to start selling the 'e-learning course' while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the 'e-learning course' will be entered into the business case.
Why is the executive's decision to deliver the benefits early appropriate for managing the business case?

  • A. Because organizations with mature project management often include the early justification for the project in the business case.
  • B. Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.
  • C. Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.
  • D. Because the business case should be updated after every increment of the 'e-learning course'.
Reveal Solution Hide Solution   Discussion   9

Correct Answer: C 🗳️

Question #9 Topic 1

During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course.
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500 in the project budget in the business case.
Is this an appropriate action, and why?

  • A. Yes, because the justification for the project should be recalculated based on the revised project budget.
  • B. Yes, because the project manager determines which costs need to be updated at the end of each stage
  • C. No, because the use of the change budget means that the project budget does not need to be increased.
  • D. No, because changes to operational costs post-project should have been included in the business case.
Reveal Solution Hide Solution   Discussion   11

Correct Answer: B 🗳️

Topic 2 - Question Set 10

Question #1 Topic 2

When updating the project plan as part of Managing a stage boundary, what else might be updated?

  • A. Exception Plan
  • B. Project Management team
  • C. Business Case
  • D. Project Initiation Documentation
Reveal Solution Hide Solution   Discussion   13

Correct Answer: A 🗳️

Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...