Question #: 183
Topic #: 1
[All 350-601 Questions]

An engineer must start a software upgrade on a Cisco Nexus 5000 Series Switch during a zone merge. What is the result of this action?

  • A. The upgrade stops
  • B. The zone merge pauses until the upgrade completes
  • C. The zone merge stops
  • D. The zone merge executes and then the upgrade completes
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5000/sw/upgrade/503_N1_1/n5000_upgrade_downgrade_503_n1_1.html

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
GuyThatTakesDumps
8 months ago
Selected Answer: A
A is correct!
upvoted 1 times
...
MaxG
1 year, 8 months ago
A is correct. Zone Server— The installation process aborts if a zone merge or zone change request is in progress.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...