Question #: 88
Topic #: 1
[All 350-601 Questions]

Which action must be performed before renumbering a Cisco UCS chassis?

  • A. Run the shut and no shut command on the connected ports.
  • B. Move the chassis to new ports on fabric interconnect.
  • C. Decommission the chassis.
  • D. Re-acknowledge the chassis.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Decommissioning is performed when a chassis is physically present and connected but you want to temporarily remove it from the Cisco UCS Manager configuration. Because it is expected that a decommissioned chassis will be eventually recommissioned, a portion of the chassis' information is retained by Cisco
UCS Manager for future use.

Renumbering a Chassis -

Before You Begin -
If you are swapping IDs between chassis, you must first decommission both chassis, then wait for the chassis decommission FSM to complete before proceeding with the renumbering steps.
Reference:
https://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/sw/cli/config/guide/3-0/b_UCSM_CLI_User_Guide_3_0/ b_UCSM_CLI_User_Guide_3_0_chapter_0100011.pdf

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Cobach
Highly Voted 1 year, 2 months ago
C is correct Decommissioning is performed when a chassisis physically present and connected but you want to temporarily remove it from the Cisco UCS Manager configuration. Because it is expected that a decommissioned chassis will be eventually recommissioned, a portion of the chassis' information is retained by Cisco UCS Manager for future use
upvoted 5 times
Cobach
1 year, 2 months ago
https://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/sw/cli/config/guide/3-0/b_UCSM_CLI_User_Guide_3_0/b_UCSM_CLI_User_Guide_3_0_chapter_0100011.pdf
upvoted 2 times
...
...
GuyThatTakesDumps
Most Recent 7 months, 2 weeks ago
C is correct!
upvoted 1 times
...
Cevel
11 months, 3 weeks ago
Selected Answer: C
C is corrent as Cobach says
upvoted 1 times
...
Smoothey
1 year, 2 months ago
If you are swapping IDs between chassis, you must first decommission both chassis, then wait for the chassis decommission FSM to complete before proceeding with the renumbering steps.
upvoted 2 times
...
designated
1 year, 5 months ago
The correct answer is C = Decommission the chassis Managing the Chassis - Cisco.pdf
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago